What stages of the project are eligible for an extension?

What stages of the project are eligible for an extension?

Where project submission timelines are affected by COVID-19, the project developer may seek an extension by submitting a request to Gold Standard. It includes but is not limited to the following key submission stages: 

  • Submission of the project within one year of start date; 
  • Successful completion of validation within two (2) years of the date of project listing; 
  • Completion of first Verification within two years (5 years in case of A/R) of project Implementation Date or Design Certification or design certification renewal, whichever is later; 
  • Submission of Design Review no later than the last date of current certification cycle; 
  • Claiming Retroactive Crediting (Extension of Retroactive Crediting period to cover delays in addition to maximum allowed period of 2 years); 
  • Submission of annual report.
    • Related Articles

    • Verified Project Activity (VPA)

      Voluntary Project Activity (VPA) / Component Project Activity (CPA) The rule update for VPA/CPA introduces flexibility to Gold Standard for the Global Goals Programme of Activities (PoAs) requirements with regards to Validation/Verification Body ...
    • Is my project eligible for retroactive crediting?

      The project will be eligible for retroactive crediting for a maximum of two years prior to the date of Gold Standard registration. However, the total duration of the crediting period of the project shall not exceed the standard crediting period ...
    • Are methane recovery project activities eligible?

      Methane recovery project activities shall be eligible for emission reductions from both methane avoidance (including from the flared biogas fraction) and non-renewable fuel substitution as long as evidence is provided on time for validation to ...
    • Are fossil-fired project activities eligible for emission reductions?

      Fossil-fired co-generation project activities shall be eligible for emission reductions from end-use energy efficiency improvements, i.e. related to on-site energy consumption. Emission reductions related to the export of heat or electricity ...
    • Where can hydropower project activities be located to be eligible for certification?

      Hydropower project activities located in High Conservation Values (HCVs) areas shall NOT be eligible for certification under Gold Standard for the Global Goals (GS4GG). Project Developers must assess if the project activity is in an HCV area.   For ...